INSIGHT · PLANNING & APPROVALS
In SA, development approval
is the last step, not a third consent.
In South Australia, a development is approved only when every consent it needs has been granted and a relevant authority indicates that it is approved (Planning, Development and Infrastructure Act 2016, s 102(1), (8)). Planning consent assesses the Planning Rules, building consent the Building Rules, and land division consent the division of land. "Building rules consent" is the repealed Development Act 1993 term for building consent. Consents need not be granted in any order (s 102(6)); once notified that consistent consents are in place, a council must grant final approval within 5 business days (reg 53(5)).

Analysed 27 October 2026 · Planning, Development and Infrastructure Act 2016 (SA), version 30.7.2026 · Planning, Development and Infrastructure (General) Regulations 2017 (SA), version 17.9.2026 · PlanSA guides Types of consent (published 6 November 2025) and Stages and timeframes · all read 27 October 2026.
Key takeaways
- Up to three consents, then one approval: Section 102(1) lists the matters a development is assessed against: the Planning Rules (planning consent), the Building Rules (building consent) and, for a division of land, the requirements in s 102(1)(c) or (d). Section 102(8): the development is approved when all relevant consents are granted and a relevant authority indicates that it is approved.
- "Building rules consent" is the old name: The 2016 Act names it building consent. Schedule 8 cl 39(2)(b) reads a reference to building rules consent under the repealed Act as including building consent under the new Act. Apart from that transitional clause, the old phrase appears once in the Act, in s 118(6)(b), on heritage places.
- Different consents, different decision makers: An accredited professional can grant planning consent only for deemed-to-satisfy development (reg 22(1)(b), (c)), and building consent within the limits of its building level (reg 25). Assessment panels, the State Planning Commission and the Minister decide the planning cases the Act gives them (ss 93 to 95). The council for the area grants final development approval (s 99(3)).
- Each consent has its own clock: Regulation 53(1) sets 5 business days for deemed-to-satisfy planning consent, 20 for performance assessed, 60 for restricted, 30 for a land division of 10 allotments or less with no public road, and 20 for building consent on a Class 1 or 10 building, before the additions the regulation lists.
- We would record each consent as its own item: A system-design recommendation: one record per consent (number, relevant authority, date, conditions, reserved matters, endorsed plans), linked to the development approval whose operative date starts the lapse clock in reg 67.
Consent by consent,
with who grants it and its clock
The periods in reg 53(1) are the periods within which the relevant authority should deal with the application. They run from the relevant day: the day the authority gives its verification notice or, if later, the day the fees are paid (reg 53(2)).
The PlanSA Stages and timeframes page states the same figures with the notification periods added in, for example 70 business days for notified performance assessed development and 95 for notified restricted development. Our page on SA planning consent times reports those PlanSA figures.
| Consent or approval | What it assesses | Who can grant it | Statutory period | What comes next | Instrument and version read |
|---|---|---|---|---|---|
| Planning consent | The Planning Rules (the Planning and Design Code) and, for impact assessed development, its impacts (s 102(1)(a)) | An assessment manager for deemed-to-satisfy and unnotified performance assessed development (reg 22(1)(a)); an accredited professional at planning level 3 or 4 for deemed-to-satisfy only (reg 22(1)(b), (c)); otherwise the assessment panel for the area (s 93); the Commission for restricted development and prescribed classes (s 94); the Minister for impact assessed development (s 95) | 5 business days deemed-to-satisfy; 20 performance assessed, plus 20 where a panel or the Commission decides; 60 restricted; plus notification, response and referral periods (reg 53(1)(a) to (c), (f) to (h)) | Building consent, if the work needs one. Matters may be reserved (s 102(3) to (5)) | PDI Act 2016 ss 93 to 95, 102, version 30.7.2026; PDI (General) Regulations 2017 regs 22, 53, version 17.9.2026. Read 27 October 2026 |
| Building consent | The Building Rules (s 102(1)(b); s 118) | An accredited professional at building level 1 for any class; level 2 up to a rise of 3 storeys and 2,000 square metres; level 3 for Class 1 or 10 up to 2 storeys and 500 square metres, levels 2 and 3 with calculations certified by an independent technical expert (reg 25); or the council where the work is referred to it (s 99(1)(c), (2)(a)) | 20 business days for a Class 1 or 10 building; 60 otherwise; plus 10 if referred to the Commission under s 118 (reg 53(1)(d), (e), (i)) | Building indemnity insurance certificate lodged where the work requires it (reg 36); then development approval | PDI Act 2016 ss 99, 102, 118, version 30.7.2026; Regulations regs 25, 26, 36, 53. Read 27 October 2026 |
| Land division consent | For general land division, the requirements in s 102(1)(c), including the Code, design standards, water and sewerage requirements and any vesting; s 102(1)(d) for community or strata title | An assessment manager (reg 22(1)(e)); an accredited professional surveyor for deemed-to-satisfy division only, with no minor variation, no vesting and no new public road (reg 22(1)(d)) | 30 business days for 10 allotments or less with no public road; 60 otherwise (reg 53(1)(ba), (e)) | Development approval; PlanSA states a land division approval must also include a planning consent | PDI Act 2016 s 102(1)(c), (d); Regulations regs 22, 53; PlanSA Types of consent. Read 27 October 2026 |
| Development approval | That all relevant consents have been granted (s 102(8)) | The council for the area (s 99(3)); the Commission where it is the relevant authority for final approval (reg 53(7)) | 5 business days after the council has notice through the portal that all consents are granted and they are consistent (reg 53(5), (6)) | Building work may start; notice of commencement 1 business day before (reg 93(1)(a)) | PDI Act 2016 ss 99, 101, 102(8); Regulations regs 53, 57, 93. Read 27 October 2026 |
The order the Act allows
and the order PlanSA describes
The Act does not fix a sequence. Section 102(2) allows an application for all of the consents a development needs or for any one or more of them, and s 102(6)(a), subject to the regulations, states that the consents need not be granted in any particular order. What the Act does fix is the end point: s 101 states that no development may be undertaken unless it is an approved development.
- PlanSA's typical sequence: For an application needing both planning and building consent, PlanSA lists twelve stages: lodgement, any request for information, referrals, public notification, planning assessment and decision, any appeal, then the building consent application, assessment and decision, full development approval, and building work commencing.
- Two consents from one authority: Where one relevant authority is asked for more than one consent at the same time, reg 53(4) adds the periods together, except that planning consent with a land division or encroachment consent takes the longest single period.
- The decision notice says work cannot start: Regulation 57(3): a notice granting planning, building or outline consent must state that building work cannot commence until the development has been approved under the Act. The notice comes with an endorsed set of approved plans (reg 57(4)).
- Reserved matters travel with the planning consent: A relevant authority may reserve its decision on a specified matter, or on planning consent itself, until further assessment or another authority's decision (s 102(3)). A reserved matter must not be fundamental to the nature of the development (s 102(5)).
Why "building rules consent"
is still the phrase people search.
The Development Act 1993 used development plan consent, building rules consent and development approval. The 2016 Act replaced the first two with planning consent and building consent, and its transitional schedule carries old references across: a reference to development plan consent is read as including planning consent (Schedule 8 cl 39(2)(a)), and a reference to building rules consent as including building consent (cl 39(2)(b)).
So a contract, a finance condition or a supplier form that asks for building rules consent is, on the transitional clause, asking for building consent. A record that holds both names against the same decision avoids a second search later.
Building consent is also needed where no building work is proposed. PlanSA states that a change in land use may require different building fire safety requirements, and so a building consent.
What a builder records
at each step
Each step produces a document with a number and a date that a later step depends on.
| Step | What to record | Why it matters (provision) |
|---|---|---|
| Lodgement and verification | Application number; the nature and category of development the authority determined; which authority is assessing which part; date of the verification notice and of fee payment | The authority determines these at verification (reg 31(1)); the later of the notice and the fee payment is the relevant day the statutory period runs from (reg 53(2)) |
| Planning consent | Consent date and the authority that granted it; each condition; each reserved matter and what it waits for; the endorsed plans | Conditions and reserved matters bind later steps (s 102(3) to (5)); the endorsed plans are part of the notice (reg 57(4)) |
| Building consent | Consent date; the accredited professional's building level or the council; the building class; any variance and its grounds; any schedule of essential safety provisions | Levels limit what a professional may consent to (reg 25); a variance must be specified in the notice (s 118(11)) |
| Building indemnity insurance | Certificate number and the date it was lodged with the relevant authority | A copy must be lodged before or with the building consent application or before commencement, depending on the case, and work must not start until it is (reg 36(2), (3)) |
| Development approval | Approval date; the operative date (later of the grant and the end of any appeal or review); every other relevant authority named on the notice; any stages the council specifies for notification | The council's notice names each relevant authority (s 99(4)); the operative date starts the lapse period (reg 67(1), (3)); specified stages need their own notices (reg 93(1)(b), (c)) |
| Commencement and completion | Date of the commencement notice and of each stage and completion notice, and who gave it | Notice is due 1 business day before commencement and before completion, with the contractor's name and licence number (reg 93(1)(a), (f), (2)) |
What we would put in a system
Where agents help here is narrow. A document intelligence agent can read a PlanSA decision notice, extract the consent type, number, authority, date, conditions and reserved matters, and draft the record; a person confirms it. No agent decides the assessment pathway, whether a consent has been validly granted, whether a reserved matter is satisfied or whether work may start. Those are for the relevant authority and your advisers.
| Field | Why it is load-bearing |
|---|---|
| One record per consent, with its number and authority | Planning, building and land division consents can come from different relevant authorities at different times (s 102(6)), and the council's approval depends on all of them. |
| The old and new name for the same decision | A document that asks for building rules consent is answered by the building consent (Schedule 8 cl 39(2)(b)). |
| Relevant day and pathway for each consent | The statutory period is counted in business days from the relevant day, and differs by pathway and class (reg 53). |
| Conditions and reserved matters, each with an owner and a status | A reserved matter or a condition can hold up the next consent or the start of work. |
| Development approval operative date and the lapse date derived from it | Regulation 67 runs from the operative date: 2 years, or 3 years where the development is lawfully commenced by substantial work within 2 years, and no lapse if it is substantially or fully completed within those 3 years. A consent not followed by a development approval lapses 2 years from its own operative date. Extensions can be granted under s 126(3). |
- Compliance & Approvals: Where each consent, its conditions and its dates are recorded.
- How long planning consent takes in SA: The published day figures and on-time rates, and what each measures.
- Development approval lapse periods by state: How long an approval lasts and what counts as starting, state by state.
- SA development site due diligence sources: The official sources checked before a site is bought.
Questions worth asking
of your own approval records
For a builder: does each job record the development approval date separately from the building consent date?
Building work cannot start on a building consent alone; the notice of consent must say so (reg 57(3)), and the approval is granted afterwards by the council (s 99(3)). The lapse period in reg 67 also runs from the development approval's operative date. General information as read on 27 October 2026, not legal advice.
For a developer: is each reserved matter tracked with what it is waiting for?
Section 102(3) lets an authority reserve a decision until further assessment, or until another authority decides under another Act. A reserved matter left untracked can surface only when the next consent is sought. General information as read on 27 October 2026, not legal advice.
For a builder using a private certifier: does the record show the accredited professional's building level?
Regulation 25 limits building levels 2 and 3 by storeys, floor area and, for level 3, building class, and requires independent certification of calculations for those levels. The level on the record is what shows the consent was within scope. General information as read on 27 October 2026, not legal advice.
Questions people ask
about SA development approval
What is building rules consent in SA?
It is the Development Act 1993 name for the assessment of building work against the Building Rules. Under the Planning, Development and Infrastructure Act 2016 it is called building consent (s 102(1)(b)), and Schedule 8 cl 39(2)(b) reads references to building rules consent as including building consent. As read on 27 October 2026; general information, not legal advice.
Planning consent vs development approval: what is the difference?
Planning consent is one consent, an assessment against the Planning Rules (s 102(1)(a)). Development approval is granted once all the consents a development needs have been granted and a relevant authority indicates the development is approved (s 102(8)), usually by the council for the area (s 99(3)). No development may be undertaken until it is approved (s 101). As read on 27 October 2026; general information, not legal advice.
What is development approval in SA?
Under s 102(8) of the Planning, Development and Infrastructure Act 2016, a development is an approved development when all relevant consents have been granted and a relevant authority has indicated that it is approved. Regulation 53(5) requires a council, once notified that all consents are granted and consistent, to grant final development approval within 5 business days. As read on 27 October 2026; general information, not legal advice.
How long does building consent take in SA?
Regulation 53(1)(d) of the PDI (General) Regulations 2017 sets 20 business days, as the period within which the relevant authority should deal with the application, for building consent on a Class 1 or 10 building, and reg 53(1)(e) 60 business days in other cases, with 10 more if the application must be referred to the State Planning Commission. The period runs from the relevant day in reg 53(2). As read on 27 October 2026; general information, not legal advice.
What is land division consent in SA?
It is the consent for dividing land, assessed against the requirements in s 102(1)(c) (or (d) for community and strata title), including the Planning and Design Code, design standards and water and sewerage requirements. PlanSA states a development approval that includes land division consent must also include a planning consent. Regulation 53 sets 30 business days for 10 allotments or less with no public road. As read on 27 October 2026; general information, not legal advice.
What this analysis
does and does not show.
Evidence note
- What it shows
- The consents a South Australian development may need under s 102 of the Planning, Development and Infrastructure Act 2016, who the Act and Regulations allow to grant each, the statutory period each carries under reg 53, how development approval follows them, and the records each step produces.
- Key facts quoted
- s 102(1), (2), (6), (8); s 101; s 99(3); ss 93 to 95; s 118; Schedule 8 cl 39(2); regs 22, 25, 31, 36, 53, 57, 67, 93 of the PDI (General) Regulations 2017. Base periods: 5, 20, 60, 30 and 20 business days, and 5 business days for final approval.
- The SA legislation register and the PlanSA portal block automated access. The Act, the Regulations and both PlanSA pages were read on 27 October 2026 through a rendering proxy and saved. PlanSA's Relevant authorities page returned a challenge through the proxy and was not read.
- The Planning and Design Code, Schedules 6, 8 and 9 of the Regulations, the Accredited Professionals Regulations 2019 and Commission practice directions were not read. The added periods in reg 53(1)(f) to (k) are described, not computed for any application.
- This covers South Australia only. It does not state how long any application will take or which authority will assess it.
- Nothing here is planning or legal advice, and it does not determine whether any consent or approval is required, valid or current.
Bring us one job's
consents and approval.
Send us the decision notices for one development: planning consent, building consent, any land division consent and the development approval. We will show you which dates and conditions your records hold for each, and which ones they leave out.
General information about published South Australian legislation and PlanSA guidance. It is not planning or legal advice and it does not determine whether any consent or approval is required, valid or current. Provisions are as read on 27 October 2026 at the versions listed.
Sources
Suggested citation: Planning, Development and Infrastructure Act 2016 (SA), version 30.7.2026, and Planning, Development and Infrastructure (General) Regulations 2017 (SA), version 17.9.2026, with PlanSA's Types of consent and Stages and timeframes guides, as read 27 October 2026. Derived figures: none.
- South Australian Legislation - Planning, Development and Infrastructure Act 2016: Version 30.7.2026 · read 27 October 2026 through a rendering proxy because the site blocks automated access · Legislation register
- South Australian Legislation - Planning, Development and Infrastructure (General) Regulations 2017: Version 17.9.2026 · read 27 October 2026 through a rendering proxy because the site blocks automated access · Legislation register
- PlanSA - Types of consent: Published 6 November 2025 (page metadata) · read 27 October 2026 through a rendering proxy because the site blocks automated access · Planning portal guide
- PlanSA - Stages and timeframes: No last-updated date shown · read 27 October 2026 through a rendering proxy because the site blocks automated access · Planning portal guide