INSIGHT · LICENSING & COMPLIANCE
The WHS management plan: one duty,
five different triggers.
A written WHS management plan is required for a construction project, and the principal contractor prepares it before work on the project commences. Under the model WHS Regulations (5 December 2025) a construction project is one where construction work costs $250,000 or more, and the plan must name who holds safety responsibilities and set out consultation, incident, site rule and SWMS arrangements. As read on 16 November 2026 the trigger is $450,000 in SA, $1,000,000 in the NT and 5 or more people working at once in WA. Victoria requires a health and safety co-ordination plan from $350,000.

Analysed 16 November 2026 · Model WHS Regulations (5 December 2025) · Qld WHS Regulation 2011 (point in time 29 March 2026) · WA WHS (General) Regulations 2022, 01-d0-00 (11 November 2026) · SA WHS Regulations 2012 (1.7.2026) · Tas WHS Regulations 2022 (current) · ACT WHS Regulation 2011, R47 (29 November 2025) · NT WHS (National Uniform Legislation) Regulations 2011 (17 July 2026) · Vic OHS Regulations 2017, Version 018 (20 October 2026) · NSW regulation text not verified · all read 16 November 2026.
Key takeaways
- The principal contractor writes it, before work starts: Model regulation 309(1): the principal contractor for a construction project must prepare a written WHS management plan for the workplace before work on the project commences. Queensland, WA, SA, Tasmania, the ACT and the NT carry the same regulation number.
- The trigger is a construction project, and the line moves by state: Regulation 292 sets it: $250,000 or more in the model, Queensland, Tasmania and the ACT (the ACT also counts loose-fill asbestos work), $450,000 or more in SA, $1,000,000 or more in the NT, and 5 or more persons working, or likely to be working, at the same time in WA.
- Five contents are required by name: Model regulation 309(2): names, positions and safety responsibilities; consultation, co-operation and co-ordination arrangements; incident arrangements; site-specific rules and how people are told them; and arrangements for collecting and reviewing SWMS.
- Victoria uses a different plan with four contents: Regulations 335 and 336 of the Victorian OHS Regulations 2017 require a health and safety co-ordination plan for projects of $350,000 or more. Its content list has no SWMS paragraph.
- We would store the plan as dated versions: A system-design recommendation: keep each revision with its date, what changed, and the date each worker was made aware of it, because model regulation 313(5) treats the plan as the initial plan and all revised versions.
When a plan is required,
and who prepares it, by state
Victoria uses the Occupational Health and Safety Act 2004 framework and its own plan name. The other jurisdictions read use the model's term, a person conducting a business or undertaking, and number the plan rules 309 to 313.
| State | Plan required | Project trigger | Who prepares it and when | How long it is kept | Instrument and version read |
|---|---|---|---|---|---|
| NSW | SafeWork NSW's Construction Work code (August 2019) says a WHS management plan; regulation text not verified (16 Nov 2026) | The code says construction work costing $250,000 or more; current regulation text not verified (16 Nov 2026) | The code says the principal contractor, before a project starts; regulation text not verified (16 Nov 2026) | not verified (16 Nov 2026) | SafeWork NSW Code of Practice: Construction Work (August 2019); read 16 Nov 2026. Work Health and Safety Regulation 2025 (NSW) not read: legislation.nsw.gov.au returned 403 |
| Victoria | Health and safety co-ordination plan (reg 335) | Construction project costing $350,000 or more; $250,000 or more if the construction contract was entered into before 1 July 2014 (reg 332 and its note) | The principal contractor, before the construction work commences; the owner is the principal contractor unless it appoints one and authorises it to manage or control the workplace (regs 333, 335) | A copy of the plan and any revisions for the duration of the construction project (reg 337(1)) | Occupational Health and Safety Regulations 2017, Version 018, effective 20 October 2026; read 16 Nov 2026 |
| Queensland | Written WHS management plan (s 309) | Construction work costing $250,000 or more (s 292) | The principal contractor, before work on the project commences (ss 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (s 313) | Work Health and Safety Regulation 2011, point in time 29 March 2026; read 16 Nov 2026 |
| South Australia | Written WHS management plan (reg 309) | Construction work costing $450,000 or more (reg 292) | The principal contractor, before work on the project commences (regs 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (reg 313) | Work Health and Safety Regulations 2012, authorised version 1.7.2026; read 16 Nov 2026 |
| WA | Written WHS management plan (reg 309) | 5 or more persons are, or are likely to be, working at the same time at a construction site (reg 292); no dollar figure | The principal contractor, before work on the project commences (regs 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (reg 313) | Work Health and Safety (General) Regulations 2022, version 01-d0-00, as at 11 November 2026; read 16 Nov 2026 |
| Tasmania | Written WHS management plan (reg 309) | Construction work costing $250,000 or more (reg 292) | The principal contractor, before work on the project commences (regs 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (reg 313) | Work Health and Safety Regulations 2022, current version viewed 16 Nov 2026 |
| ACT | Written WHS management plan (s 309) | Construction work costing $250,000 or more, or work involving demolition or refurbishment of a structure containing loose-fill asbestos insulation (s 292) | The principal contractor, before work on the project commences (ss 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (s 313) | Work Health and Safety Regulation 2011, Republication 47, effective 29 November 2025; read 16 Nov 2026 |
| NT | Written WHS management plan (reg 309) | Construction work costing $1,000,000 or more (reg 292), from 28 May 2026; the earlier reg 292 continues for a project whose construction work began before then (reg 837) | The principal contractor, before work on the project commences (regs 293, 309) | Until the project is completed; at least 2 years after a connected notifiable incident (reg 313) | Work Health and Safety (National Uniform Legislation) Regulations 2011, as in force at 17 July 2026; read 16 Nov 2026 |
Who the principal contractor is,
and what the plan sits beside.
Model WHS regulation 293 makes the business that commissions a construction project its principal contractor, unless that business engages another business as principal contractor and authorises it both to have management or control of the workplace and to discharge the principal contractor's duties under Chapter 6.
- A home owner who engages a builder: Model regulation 293(3): where an individual owner of residential premises engages a business for a construction project, the business engaged is the principal contractor if it has management or control of the workplace. Victoria's regulation 333(2) reaches domestic premises in similar terms.
- Only one at a time: Model regulation 293(4): a construction project has only one principal contractor at any specific time.
- Telling people before they start: Model regulation 310: the principal contractor must ensure, so far as is reasonably practicable, that each person who is to carry out construction work is made aware of the plan's content, and of the right to inspect it, before commencing work. Victoria's regulation 337(2) requires awareness of the plan and access to it.
- Keeping it current: Model regulation 311 requires the plan to be reviewed and as necessary revised to remain up to date, and people carrying out construction work to be made aware of any revision. Victoria's regulation 335(b) requires the plan to be monitored, maintained and kept up to date for the duration of the work.
- Getting the SWMS in: Model regulation 312: the principal contractor must take all reasonable steps to obtain a copy of the safe work method statement before high risk construction work commences. Our page on SWMS by state covers what those statements must hold.
- Duties beyond the plan: Model regulation 314 requires the principal contractor to put in place arrangements for compliance with listed divisions of Part 3.2, which include general workplace facilities, first aid and emergency plans. Regulation 315 adds materials and waste, plant not in use, nearby traffic and essential services.
- A sign at the gate: Model regulation 308 requires signs showing the principal contractor's name and telephone numbers, including after hours, and the site office location, clearly visible from outside the workplace.
What the plan must contain,
and what is only customary.
Model WHS regulation 309(2) lists five things a WHS management plan must include. Safe Work Australia's model Code of Practice: Construction work (November 2024) lists further items a plan may also include.
Safe Work Australia's model Code also says a principal contractor may prepare a generic plan for several projects, but it must be reviewed for the specific project and workplace and revised as necessary. The Code provides a template in Appendix H and a completed example in Appendix I.
| Field | What it holds | Label |
|---|---|---|
| People with safety roles | Names, positions and health and safety responsibilities of everyone whose role involves specific safety responsibilities for the project | Required by model reg 309(2)(a); Vic reg 336(a) |
| Consultation and co-ordination | Arrangements between the businesses on site for consultation, co-operation and co-ordination of their duties | Required by model reg 309(2)(b); Vic reg 336(b) (co-ordination) |
| Incident arrangements | How work health and safety incidents that occur will be managed | Required by model reg 309(2)(c); Vic reg 336(c) |
| Site rules | Site-specific health and safety rules, and how everyone at the workplace is informed of them | Required by model reg 309(2)(d); Vic reg 336(d) |
| SWMS handling | Arrangements for collecting, and any assessment, monitoring and review of, safe work method statements at the workplace | Required by model reg 309(2)(e); not in Vic reg 336 |
| Further site matters | Hazardous chemicals register and storage, plant use and storage, a traffic management plan, essential services information, security and public safety, licences and training, psychosocial hazards | Customary: listed as items a plan may also include in Safe Work Australia's model Code (November 2024) |
| Version and revision log | Date of each revision, what changed, and why | Our design, so the record shows which version applied on a day (model reg 313(5) counts all revised versions as the plan) |
| Awareness record | Each worker's name, the plan version shown, and the date, before that worker started | Our design, to show the duty in model reg 310 and reg 311(2) was met |
| Retention end date | Project completion date, any connected notifiable incident, and the date keeping can end | Our design, built on model reg 313(1) and (2); Vic reg 337(1) runs for the duration of the project |
A WHS management plan is not a SWMS,
and neither is a council's plan.
Under the model WHS Regulations a WHS management plan covers the whole construction project and is prepared by the principal contractor, while a safe work method statement covers one item of high risk construction work and is prepared by the business doing that work.
- The plan points to the SWMS: Model regulation 309(2)(e) requires the plan to set out how SWMS are collected, assessed, monitored and reviewed on site. It does not replace them.
- A council plan answers to a different body: A construction management plan asked for by a council deals with the site's effect on roads, neighbours and the public. Our page on council construction management plans covers who asks for one.
- A safety management plan, by another name: Searches for a safety management plan or a site safety plan usually mean this document. The instruments read use the term WHS management plan, or in Victoria health and safety co-ordination plan.
What a national review
has proposed, and its status.
Safe Work Australia's Best Practice Review of the model WHS laws, published in October 2026, recommends amending the model definition of a construction project to adopt WA's approach, which counts people on site rather than dollars.
- What it says: The final report notes that SA and the NT have different monetary thresholds from the model, and that WA defines a construction project by 5 or more persons working at the same time. It recommends amending the definition in line with the WA variation (Appendix F, item 2).
- Why it says so: The report states that a headcount threshold would be consistent over time and avoid regional building prices and inflation changing which regulations apply.
- Status at 16 November 2026: A recommendation to WHS ministers, not an amendment. Safe Work Australia's review page says the report went to ministers on 4 August 2026 and ministers agreed to publish it in October 2026. We found no amending instrument and no announced date.
What we would put in a system
A WHS management plan is useful as evidence when it can show which version was in force on a given day, and who had been told about it.
Where agents help here is narrow. A compliance agent can read a contract and site diary, propose whether a project crosses the state trigger, draft the plan's people and contacts table from the job record, and flag a revision that no worker has been shown. A person confirms. No agent decides whether a project is a construction project, who the principal contractor is, or whether a plan complies.
| Field | Why it is load-bearing |
|---|---|
| Project trigger, state and read date | The same $400,000 job is a construction project in Queensland and not in SA or the NT, and in WA it depends on headcount. Holding the trigger and the instrument version read shows why a plan was or was not prepared. |
| Who the principal contractor is, and the authorisation | Model reg 293(2) turns on engagement and authorisation to manage or control the workplace. The appointment document belongs with the plan. |
| Plan prepared date and first work date | Model reg 309(1) and Vic reg 335(a) require the plan before work commences, so the two dates need to be comparable. |
| Version, revision date and reason | Model reg 311 ties review to keeping the plan up to date; a dated version shows what applied that day. |
| Awareness per worker per version | Model regs 310 and 311(2) require the principal contractor to ensure, so far as is reasonably practicable, that people carrying out construction work on the project are made aware before they start and after each revision. |
| Completion date, notifiable incidents and retention end | Model reg 313 runs to completion, or at least 2 years after a connected notifiable incident. |
- SWMS and high risk construction work by state: The statements the plan has to collect and review.
- Construction site diary: what to record: The daily record a plan revision should be able to point to.
- Construction management plans: council requirements: A different plan, for a different authority.
- Compliance: Where dated compliance records sit in an operating system.
Questions worth asking
of your own safety records
For a builder working in more than one state: does your job set-up test the project against each state's own trigger?
As read on 16 November 2026 the line was $250,000 in Queensland, Tasmania and the ACT (the ACT also covers demolition or refurbishment of a structure containing loose-fill asbestos insulation, at any cost), $350,000 in Victoria for contracts from 1 July 2014, $450,000 in SA, $1,000,000 in the NT, and 5 or more persons working, or likely to be working, at once in WA. General information, not legal or WHS advice.
For a principal contractor: can you show that each worker saw the plan before starting construction work?
Model regulation 310 requires the principal contractor to ensure, so far as is reasonably practicable, that each person who is to carry out construction work in connection with the project is made aware of the plan's content, and of the right to inspect it, before commencing work. A dated record against the worker and the plan version is what answers the question.
For a WA builder: who counts heads on site?
WA regulation 292 turns on 5 or more persons working, or likely to be working, at the same time. That is a fact about the programme, so the programme or diary is where the evidence sits.
For a safety manager: does a notifiable incident change your archive date?
Model regulation 313(2) requires the plan to be kept for at least 2 years after a connected notifiable incident. If archiving runs off project completion alone, the incident has to reach that record.
Questions people ask
about WHS management plans
What is a WHS management plan?
Under regulation 309 of the model Work Health and Safety Regulations (5 December 2025), it is a written plan the principal contractor for a construction project prepares before work on the project commences. It names the people with safety responsibilities and sets out consultation, incident, site rule and SWMS arrangements for the workplace. As read on 16 November 2026.
When is a WHS management plan required for a construction site?
When the work is a construction project under regulation 292. As read on 16 November 2026 that was construction work costing $250,000 or more in the model regulations, Queensland, Tasmania and the ACT, $450,000 or more in SA, $1,000,000 or more in the NT, and 5 or more persons working, or likely to be working, at the same time at a construction site in WA. The ACT also covers demolition or refurbishment of a structure containing loose-fill asbestos insulation, whatever the cost. The NT figure applies from 28 May 2026; the earlier regulation 292 continues for a project whose construction work began before then (reg 837). NSW regulation text was not verified.
Who prepares a WHS management plan?
The principal contractor. Under model WHS regulation 293 that is the business commissioning the construction project, or the business it engages as principal contractor and authorises both to have management or control of the workplace and to discharge the principal contractor's duties under Chapter 6. Where an individual home owner engages a builder that has management or control of the workplace, the builder is the principal contractor. As read on 16 November 2026.
What must a WHS management plan for construction include?
Model WHS regulation 309(2) requires five things: the names, positions and safety responsibilities of people with specific safety roles; arrangements for consultation, co-operation and co-ordination; arrangements for managing incidents; site-specific rules and how people are told them; and arrangements for collecting and reviewing safe work method statements. As read on 16 November 2026.
Does Victoria require a WHS management plan for construction?
Victoria's Occupational Health and Safety Regulations 2017 (Version 018) require a health and safety co-ordination plan instead, under regulations 335 and 336, for construction projects costing $350,000 or more where the contract was made on or after 1 July 2014. Its four required contents correspond to the model's first four; there is no SWMS paragraph. As read on 16 November 2026.
Is there a WHS management plan example or template?
Safe Work Australia's model Code of Practice: Construction work (November 2024) includes a template and a completed example in its appendices. A template does not change what regulation 309 requires, and a generic plan must still be reviewed for the specific project, according to the Code.
What this analysis
does and does not show.
Evidence note
- What it shows
- The construction project trigger, the duty to prepare a WHS management plan or its Victorian equivalent, its required contents, and how long it is kept, in the model regulations, Queensland, WA, SA, Tasmania, the ACT, the NT and Victoria, read from each instrument on 16 November 2026; and the status of one national review recommendation.
- Key facts quoted
- Model regs 292, 293, 308 to 315: $250,000, plan before work commences, five contents, keep to completion or 2 years after a notifiable incident. SA reg 292: $450,000. NT reg 292: $1,000,000, with reg 837 keeping the earlier rule for projects begun before 28 May 2026. WA reg 292: 5 or more persons. ACT s 292: $250,000 or loose-fill asbestos. Vic regs 332, 333, 335 to 337: $350,000, four contents, keep for the duration of the project.
- NSW regulation text is not verified. legislation.nsw.gov.au returned 403 on 16 November 2026 and we did not route around it. SafeWork NSW's Construction Work code is dated August 2019, before the Work Health and Safety Regulation 2025 (NSW), so its statements are shown as the regulator's dated statements.
- Safe Work Australia's model Code of Practice is guidance on how to meet the regulations. Whether it is approved in a given state was not checked here.
- We did not read the WHS Acts, penalty provisions or enforcement policies, or check how any regulator applies the cost of construction work in practice. Victoria values a project as section 11 of its Security of Payment Act 2002 values construction work (reg 332(2)).
- We did not assess whether any project is a construction project, who its principal contractor is, or whether any plan complies.
- Nothing here is legal or WHS advice, and it is not a template.
Bring us one plan
and the day it changed.
Send a WHS management plan, its revisions, and the record of who was shown each version. We will show you whether your records can say which version applied on a given day, under which state trigger, and when keeping can end.
This article is general information about published Australian workplace safety regulations. It is not legal or WHS advice and it does not determine whether any project needs a plan or whether any plan complies. Instruments as read on 16 November 2026 at the versions listed. NSW regulation text was not verified.
Sources
Suggested citation: Cyberate, "The WHS management plan: one duty, five different triggers", Insights, analysed 16 November 2026. Derived figures: none.
- Safe Work Australia - Model Work Health and Safety Regulations: PCC [360], 5 December 2025 · read 16 November 2026 · National model regulations
- Queensland Legislation - Work Health and Safety Regulation 2011: Current version, point in time 29 March 2026 · read 16 November 2026 · Legislation register
- Western Australian Legislation - Work Health and Safety (General) Regulations 2022: Version 01-d0-00, as at 11 November 2026 · read 16 November 2026 · Legislation register
- South Australian Legislation - Work Health and Safety Regulations 2012: Authorised version 1.7.2026 · read 16 November 2026 · Legislation register
- Tasmanian Legislation - Work Health and Safety Regulations 2022: Current version viewed 16 November 2026 · read 16 November 2026 · Legislation register
- ACT Legislation Register - Work Health and Safety Regulation 2011: Republication No 47, effective 29 November 2025 · read 16 November 2026 · Legislation register
- NT Legislation - Work Health and Safety (National Uniform Legislation) Regulations 2011: Reprint as in force at 17 July 2026 · read 16 November 2026 · Legislation register
- Victorian Legislation - Occupational Health and Safety Regulations 2017: Authorised Version No. 018, effective 20 October 2026 · read 16 November 2026 · Legislation register
- Safe Work Australia - Model Code of Practice: Construction work: November 2024 · read 16 November 2026 · Model code of practice
- SafeWork NSW - Code of Practice: Construction Work: August 2019 · read 16 November 2026 · Regulator code of practice, predates the current regulation
- Safe Work Australia - Best Practice Review of the model WHS laws: Final report: October 2026 · read 16 November 2026 · Review report to WHS ministers
RELATED READING
Other readings on the same records.
- No regulation sets a stop-work temperature. One territory code names 37 degrees: Heat duties in all eight jurisdictions, WA's regulation 41A, the ACT code's 37 degrees, and what the on-site award requires to be recorded. (Licensing & Compliance)
- Is the NCC law? Only through each state's own Act: How each state gives the NCC legal effect, when referenced Australian Standards bind, and where the $42.7 million free-standards measure stands. (Licensing & Compliance)
- AI document review reads the set. A named person confirms what it found: By document type: what an AI tool can extract, what a person must confirm and why, and the record to keep, from national AI guidance and NSW rules. (AI Governance & Compliance)