INSIGHT · LICENSING & COMPLIANCE

No regulation sets a stop-work temperature.
One territory code names 37 degrees.

No WHS or OHS regulation read for this article sets a temperature at which construction work must stop. The model WHS Regulations (5 December 2025) require a business, so far as is reasonably practicable, to ensure workers in extremes of heat can work without risk to health and safety (regulation 40(f)). WA adds regulation 41A. The ACT's extreme temperatures code says a construction stop threshold should consider whether temperatures are expected above 37 degrees. As read on 16 November 2026.

Silhouette of a bricklayer in a hard hat and vest laying bricks against a low orange sun

Analysed 16 November 2026 · Model WHS Regulations (5 December 2025) · Qld, WA, SA, Tas, ACT and NT WHS regulations at the versions in the table · Vic OHS Regulations 2017, Version 018 (20 October 2026) · ACT Extreme Temperatures Code of Practice, NI2025-607 (effective 14 November 2025) · Building and Construction General On-site Award 2020, consolidated to 1 July 2026 · Safe Work Australia heat FAQ and guide · regulator pages for Victoria, NSW, SA and WA · NSW regulation text not verified · all read 16 November 2026.

Key takeaways

  • A duty, not a number: Model WHS regulation 40(f) requires a business, so far as is reasonably practicable, to ensure that workers carrying out work in extremes of heat or cold are able to carry out work without risk to health and safety. Safe Work Australia's heat FAQ answers "No" to whether there is a maximum temperature at which workers are required to stop.
  • WA has its own heat regulation: Regulation 41A of the WA Work Health and Safety (General) Regulations 2022 requires work practices arranged so workers are protected from extremes of heat and cold, and, in a structure, heating and cooling so far as is reasonably practicable.
  • The ACT code puts 37 degrees in writing: The ACT's Managing the Risks Associated with Extreme Temperatures Code of Practice (effective 14 November 2025) says the construction stop threshold should consider whether temperatures are expected to be higher than 37 degrees. In that code, should means recommended.
  • The award covers stopping and pay, for award-covered work: Clause 24 of the Building and Construction General On-site Award 2020 treats extreme high temperature as inclement weather where it is not reasonable or unsafe to continue, requires the employer to record stop and resume times, and gives no temperature.
  • A national change is a recommendation only: Safe Work Australia's Best Practice Review (October 2026) recommends new model WHS Regulations to regulate extreme heat. At 16 November 2026 we found no draft regulation.

Heat rules
in eight jurisdictions

The model WHS Act and the state WHS Acts were not read. Regulator pages are guidance, not law. The ACT code's own words separate must, a legal requirement, from should, a recommendation.

StateHeat duty in the regulationsStop-work temperature in an instrument readWhat the regulator saysInstrument and version read
NSWRegulation text not verified (16 Nov 2026)Regulation text not verified (16 Nov 2026)SafeWork NSW's Extreme heat: the basics page says the WHS Regulation does not state a precise temperature at which workers should stop workWork Health and Safety Regulation 2025 (NSW) not read: legislation.nsw.gov.au returned 403 on 16 Nov 2026. SafeWork NSW page, no date shown, read 16 Nov 2026
VictoriaWe found no regulation on heat in the OHS Regulations 2017; the general duties sit in the OHS Act 2004, which was not readNone foundWorkSafe Victoria says there is no maximum temperature set under the OHS Act 2004 or the OHS Regulations 2017 for a worker to stop workingOccupational Health and Safety Regulations 2017, Version 018, effective 20 October 2026; WorkSafe Victoria page, no date shown; read 16 Nov 2026
QueenslandWorkers in extremes of heat or cold able to work without risk, so far as is reasonably practicable (s 40(f)); drinking water (s 41)None foundRegulator page not verified (16 Nov 2026): worksafe.qld.gov.au returned 403Work Health and Safety Regulation 2011, point in time 29 March 2026; read 16 Nov 2026
South AustraliaWorkers in extremes of heat or cold able to work without risk, so far as is reasonably practicable (reg 40(f)); drinking water (reg 41)None foundSafeWork SA says the legislation does not specify a stop work temperatureWork Health and Safety Regulations 2012, authorised version 1.7.2026; SafeWork SA page, no date shown; read 16 Nov 2026
WAReg 40(f) and reg 41 as the model, plus reg 41A: work practices arranged so workers are protected from extremes of heat and cold, and heating and cooling in a structure so far as is reasonably practicableNone foundWorkSafe WA's Working safely in hot conditions page (last updated 23 October 2026); we found no stop-work temperature on itWork Health and Safety (General) Regulations 2022, version 01-d0-00, as at 11 November 2026; read 16 Nov 2026
TasmaniaWorkers in extremes of heat or cold able to work without risk, so far as is reasonably practicable (reg 40(f)); drinking water (reg 41)None foundRegulator page not verified (16 Nov 2026): worksafe.tas.gov.au returned 403Work Health and Safety Regulations 2022, current version viewed 16 Nov 2026
ACTWorkers in extremes of heat or cold able to work without risk, so far as is reasonably practicable (s 40(f)); drinking water (s 41)No number in the regulation. The approved Extreme Temperatures Code says a construction stop threshold should consider whether temperatures are expected to be higher than 37 degreesRegulator page not readWork Health and Safety Regulation 2011, Republication 47, effective 29 November 2025; Extreme Temperatures Code of Practice, NI2025-607, effective 14 November 2025; read 16 Nov 2026
NTWorkers in extremes of heat or cold able to work without risk, so far as is reasonably practicable (reg 40(f)); drinking water (reg 41)None foundRegulator page not verified (16 Nov 2026): worksafe.nt.gov.au returned 403Work Health and Safety (National Uniform Legislation) Regulations 2011, as in force at 17 July 2026; read 16 Nov 2026

What temperature do you stop work?
The regulators answer the same way.

Safe Work Australia's Working in heat FAQ asks whether there is a maximum temperature at which workers are required to stop work, and answers: "No." It says a single stop-work temperature cannot account for humidity, air flow, the intensity and duration of the work, and whether workers are fit and acclimatised.

  • Instead, a risk duty: The same FAQ says businesses must eliminate or minimise risks so far as is reasonably practicable. Safe Work Australia's guide on working in heat (October 2021) points to regulation 40 and describes identifying the hazard, assessing the risk and choosing controls.
  • Victoria: WorkSafe Victoria: no maximum temperature is set under the OHS Act 2004 or the OHS Regulations 2017 for a worker to stop working, and some workplaces may have their own policy.
  • NSW and SA: SafeWork NSW says the WHS Regulation does not state a precise temperature at which workers should stop work. SafeWork SA says the legislation does not specify a stop work temperature; 30 degrees appears on its page only in a hazard identification question.
  • Who can stop unsafe work: Safe Work Australia's FAQ says a trained health and safety representative can direct a worker in their work group to cease unsafe work, where there is a reasonable concern about a serious risk from an immediate or imminent hazard. Consultation and an attempt to resolve the issue come first, unless the risk is so serious and immediate that consulting first is not reasonable, and the workplace must be informed of the direction.

The ACT code:
the one number in writing.

The ACT's Work Health and Safety (Managing the Risks Associated with Extreme Temperatures Code of Practice) Approval 2025, NI2025-607, took effect on 14 November 2025. It is the only instrument read for this article that puts a temperature beside a construction stop decision.

The code applies in the ACT. Outside the ACT, no instrument read for this article puts a number on it.

  • 37 degrees, as a consideration: "For the building and construction industry, this threshold to stop work should consider whether temperatures are expected to be higher than 37 degrees." The code defines should as a recommended course of action.
  • 35 to 37 degrees: Where heat stress is likely even with controls, the code says workers should be moved to an area unaffected by heat or to an air-conditioned site shed until the temperature is acceptable.
  • Breaks and rotation: The code gives, as an example of effective controls in construction, hourly drink breaks of about 5 to 10 minutes in the shade and job rotation.
  • A temperature management plan: The code says a workplace temperature management plan should be developed with workers and their health and safety representatives, covering monitoring, agreed controls and stop parameters. It includes a template at Appendix E.

The award: stopping, recording and pay,
for award-covered work.

The Building and Construction General On-site Award 2020 sets terms for employees it covers. It is not a WHS law, and enterprise agreements may set different terms. Clause 24, inclement weather, applies only to general building and construction and the civil construction sector (clause 24.1).

Our page on the July 2026 award wage increase covers the pay rates. Award coverage of any business or worker was not assessed.

  • Extreme high temperature, no number: Clause 24.2 defines inclement weather to include extreme high temperature where it is not reasonable or is unsafe for employees to continue working in those conditions.
  • Confer within 60 minutes: Clause 24.3: when asked by the employees or their representative, the employer must confer within a reasonable time, not exceeding 60 minutes, to decide whether those conditions apply.
  • Record stop and resume times: Clause 24.4: the time work stops and the time it resumes will be recorded by the employer. Clause 24.5: an affected employee is not required to start or continue work where it is unreasonable or unsafe.
  • Paid time, with a cap: Clause 24.7: where an employee cannot perform any work at any location because of inclement weather, payment is at the ordinary hourly rate for ordinary hours, to a maximum of 32 hours in any 4-week period for each employee, and subject to adherence to the terms of clause 24.
  • Hot work is separate: Clause 18.6: where the temperature has been raised by artificial means to 46 degrees or above, an employee working more than 2 hours is entitled to 20 minutes' rest after every 2 hours without loss of pay.

What a national review
has proposed for heat.

Safe Work Australia's Best Practice Review of the model WHS laws, published in October 2026, recommends that the model WHS Regulations be amended to regulate extreme heat, air quality and vector-borne diseases.

  • Recommendation 20: A Safe Work Australia strategy on climate change that includes new model WHS Regulations on extreme heat, monitors how WHS laws are applied to extreme weather, and makes new regulations or codes where gaps are found.
  • Codes for outdoor industries: The report says industries involving outdoor work, including construction and civil works, will particularly benefit from advice on heat-related risks through industry codes.
  • Status at 16 November 2026: A recommendation to WHS ministers, not a regulation. We found no draft model regulation on heat and no announced date. Each state would decide separately whether to adopt one.

A heat record,
field by field.

No regulation read prescribes a heat log. Its fields differ in origin: some rest on a legal duty, some on customary practice, and some are design choices.

We found no retention period for a heat record in the regulations read. A record is evidence of what was done; it does not decide whether a duty was met.

FieldWhat it holdsLabel
Date, site and work areaWhere and when the reading and controls applyCustomary
Forecast and measured conditionsTemperature, humidity, and any heat index usedCustomary: Safe Work Australia's heat guide describes simple heat indices; the ACT code says monitoring should be part of a temperature management plan
Hazards identifiedDirect sun, radiant surfaces, enclosed spaces, heavy physical workCustomary: Safe Work Australia's heat guide includes a hazard checklist
Controls in placeShade, rescheduling, rotation, rest breaks, coolingDuty under model reg 40(f), so far as is reasonably practicable; WA reg 41A; the specific controls are a choice
Drinking waterWhere it is and that it is suppliedFacilities duty under model reg 41, so far as is reasonably practicable; recording it is our design
Stop parameters in the site planThe site's own agreed stop point and its versionRecommended in the ACT by the Extreme Temperatures Code; elsewhere our design
Request to confer, and time conferredWho asked, when, and when the employer conferredAward cl 24.3 sets the 60-minute limit for award-covered work; recording it is our design
Stop time and resume timeWhen work stopped and resumed for heatRequired by award cl 24.4 for award-covered general building and civil construction work
Hours lost per employeeRunning total in the 4-week periodOur design, against the award cl 24.7 cap of 32 hours
Who confirmedThe supervisor who confirmed the entryOur design

What we would put in a system

A heat record earns its keep when the conditions, the controls and the stop decision sit on the same dated line as the site diary.

Where agents help here is narrow. A compliance agent can pull the day's forecast, draft the heat entry with the site's own plan parameters beside it, total hours lost against the award cap, and remind the supervisor when a reading is due. A person decides whether work stops. No agent decides whether conditions are unsafe or whether a duty is met. This is a record design, not a heat policy and not WHS advice.

FieldWhy it is load-bearing
Conditions with time of readingNo regulation read sets a stop-work number, and the ACT code's 37 degrees is a consideration rather than a fixed trigger, so the record of what was measured, and when, is the evidence of the risk assessment.
Controls against the plan versionModel reg 40(f) is a reasonably practicable duty; the record shows which controls the site chose that day.
Stop and resume timesAward cl 24.4 requires them for award-covered work, and they feed pay under cl 24.7.
Who decided, and who confirmedA trained health and safety representative can, in the circumstances Safe Work Australia describes, direct unsafe work to cease; the record should show who directed or decided each stop, when, and on what stated basis.

Questions worth asking
of your own heat records

For a site manager: could you show, for last summer's hottest day, which controls were in place and when work stopped?

Model WHS regulation 40(f) is a reasonably practicable duty with no number in it, so the dated record of conditions and controls is what shows how it was met. General information, not legal or WHS advice.

For an employer under the on-site award: are stop and resume times recorded in the same place as pay?

Clause 24.4 of the Building and Construction General On-site Award 2020 requires the employer to record them for general building and civil construction work, and clause 24.7 caps paid inclement weather time at 32 hours per 4 weeks.

For an ACT builder: is there a temperature management plan with agreed stop parameters?

The ACT Extreme Temperatures Code (effective 14 November 2025) says one should be developed with workers and their representatives, and gives a template at Appendix E.

For a WA principal contractor: do site sheds and offices have heating and cooling?

WA regulation 41A(b) requires heating and cooling, so far as is reasonably practicable, where the workplace is in a structure, alongside the regulation 41A(a) duty on work practices.

Questions people ask
about heat on construction sites

At what temperature do you stop work in construction in Australia?

No WHS or OHS regulation read for this article sets one. Safe Work Australia's heat FAQ answers "No" to whether a maximum temperature requires work to stop. The ACT's Extreme Temperatures Code (effective 14 November 2025) says a construction stop threshold should consider whether temperatures are expected to be higher than 37 degrees. As read on 16 November 2026.

Is there a maximum temperature for working outside in Victoria?

WorkSafe Victoria says no maximum temperature is set under the OHS Act 2004 or the OHS Regulations 2017 for a worker to stop working, and that some workplaces have their own policy. We found no heat regulation in the OHS Regulations 2017, Version 018. As read on 16 November 2026.

What does the building award say about extreme heat?

Clause 24 of the Building and Construction General On-site Award 2020, for general building and civil construction, treats extreme high temperature as inclement weather where continuing is not reasonable or unsafe, requires conferring within 60 minutes when asked, records stop and resume times, and, where no work can be performed at any location, pays lost ordinary hours up to 32 hours per 4 weeks. It names no temperature.

What are the WA heat regulations for construction workers?

The WA Work Health and Safety (General) Regulations 2022 carry regulation 40(f), on working in extremes of heat or cold so far as is reasonably practicable, and add regulation 41A: work practices arranged so workers are protected from extremes of heat and cold, and, where the workplace is in a structure, heating and cooling so far as is reasonably practicable. No temperature appears. Version 01-d0-00, as read on 16 November 2026.

Will there be a national heat regulation?

Safe Work Australia's Best Practice Review (October 2026) recommends new model WHS Regulations on extreme heat, in Recommendation 20. It is a recommendation to WHS ministers; we found no draft and no date at 16 November 2026.

What this analysis
does and does not show.

Evidence note

What it shows
The heat duty in the model WHS Regulations and in the Queensland, WA, SA, Tasmanian, ACT and NT regulations, read from each instrument on 16 November 2026; the absence of a heat regulation in Victoria's OHS Regulations 2017; the ACT Extreme Temperatures Code; clauses 18.6 and 24 of the on-site award; Safe Work Australia's heat FAQ and guide; four regulator pages; one national review recommendation.
Key facts quoted
Model regs 40(f), 41. WA reg 41A. ACT code: 37 degrees as a consideration, 35 to 37 degrees, hourly drink breaks of about 5 to 10 minutes. Award cl 24.1 to 24.5 and 24.7: 60 minutes, stop and resume times, 32 hours per 4 weeks; cl 18.6: 46 degrees by artificial means. Derived figures: none.
  • NSW regulation text is not verified. legislation.nsw.gov.au returned 403 on 16 November 2026 and we did not route around it; the NSW row rests on SafeWork NSW's page, which shows no date.
  • The Queensland, Tasmanian and NT regulators' heat pages returned 403 and were not read. The ACT regulator's page was not read.
  • The WHS and OHS Acts were not read. Enterprise agreements, site policies and other awards were not read and may set different terms.
  • We did not assess whether any site's controls, plan or stop decision meet any duty, or whether the award covers any business or worker.
  • Nothing here is legal, industrial or WHS advice, and it is not a heat policy.

Bring us last summer's
hottest week on site.

Send the site diary, the heat or weather log and the timesheets for one hot week. We will show you whether your records hold the conditions, the controls and the stop and resume times on the same dated line.

This article is general information about published Australian workplace safety instruments and one modern award. It is not legal, industrial or WHS advice and it does not determine whether any site's controls or stop decisions comply. Instruments as read on 16 November 2026 at the versions listed. NSW regulation text was not verified.